Earlier this year in April, FCT was awarded a contract to deliver 10 Gyro-Therm™ burners for Eurocement across 5 plants in Russia: Kavkazcement, Oskolcement, Nevyanskiy Cement, Maltsovsky Portlandcement and Belgorodsky Cement. The burners will be capable of firing 100% natural gas and solid alternative fuels.

Now, we are extremely excited to announce that only 10 weeks later, we have successfully designed and delivered 8 of the burners, with the remaining two to be delivered in late July. Commissioning is expected for the next months.

We would like to thank our dedicated team for all their hard work in helping deliver this project to our valued customers within this record timeline!

To read more about the contract, please click: https://lnkd.in/gVSUnHZ

To learn how FCT’s revolutionary Gyro-Therm™ burner technology can deliver simultaneous reduction in kiln fuel consumption, production increase and NOx emissions reduction, please visit: https://lnkd.in/gCRARpt